2.3 Significant change from baseline or previous comparable quarter (undesirable outcome)

CFA: Timely delivery of major programs and projects

CFA reported 38% of major programs and projects as having an overall status of ‘on track’ at the end of Q2 against a 3-year baseline of 55%. This is the second reporting period in which the results were below the baseline. CFA have advised inconsistencies in project delivery practices, controls and monitoring across portfolios contributed to the result.

Figure 6: Timely delivery of major programs and projects